RPCL Documentation
Rusumo Power Company Limited (RPCL) is a special purpose company incorporated under the laws of Rwanda and was registered with Rwanda Development Board in 2013. It also maintains a certificate of compliance in Tanzania.
RPCL is jointly and equally owned by the Governments of Burundi, Rwanda and Tanzania. RPCL has rights to develop, construct, own, and operate the 80MW Regional Rusumo Falls Hydroelectric Project located on the Kagera river at Rusumo border between Rwanda and Tanzania. Each country will get approximately 27MW during operation of the plant.
Rusumo Power Company Limited(RPCL) Board Meeting 2016
The 2012 Tripartite Agreement guided to formation of:
• Council of Ministers for Energy (COM)
• Project Implementation Committee (PIC)
• Technical Advisory Committee (TAC)
• Project Steering Committee (PSC)
• Rusumo Power Company Limited (RPCL)
• RPCL Board of Directors
Other key agreements:
• 2013 Shareholders Agreement
• 2013 Implementation Agreement
• 2013 Financing Agreements
• 2013 Subsidiary Agreements
• 2013 Project Agreement
• 2013 Power Purchase Agreements
• 2014 Project Implementation Support Agreement
Financial Arrangement: World Bank Financing the Power Plant
• Financial negotiations: July 2013
• Board approval: August 2013
• Financial agreements: October 2013
• Project effectiveness: July 2013
|